Yes. DA compliance triggers per 11B-202 of LABC, when there is an alteration to a building or site as defined in Chapter 2, Section 202 of the Building Code.
However, some exceptions apply, such as projects only consisting of heating, ventilation, air conditioning, or cosmetic works like painting, wallpapering, etc. There are also general exceptions that exempt DA compliance, such as construction sites, raised areas, and machinery spaces, per 11B-203 of the LABC.
However, some exceptions apply, such as projects only consisting of heating, ventilation, air conditioning, or cosmetic works like painting, wallpapering, etc. There are also general exceptions that exempt DA compliance, such as construction sites, raised areas, and machinery spaces, per 11B-203 of the LABC.