Within two (2) years after the service date of the Order to Comply, a structural analysis and plans to either retrofit or demolish, or proof of previous retrofit shall be submitted to the Department for review if the building meets the minimum requirements of this ordinance.

2

Within three-and-a-half (3 ½) years after the service date of the Order to Comply, obtain all permits for retrofit or demolition of the building.

3 ½

Within seven (7) years after the service date of the Order to Comply, complete construction or demolition work and finalize permits.

7

Question label
What are the time limits to comply?